Has attained tangible milestones in preparing for the construction of the Phase-2 Matawinie Mine through key procurement activities, detailed engineering, construction planning and community investment. Among these is the awarding of the 120kV electrical substation to ABB (NASDAQ: ABBNY) as part of the construction preparation and strategy to secure long-lead items for the establishment of an all-electric 103,000-tpa graphite mining and concentrator complex at Matawinie, 120 kilometers north of Montréal. Nouveau Monde Graphite Inc. shares V.NOU are trading up $0.02 at $1.92.